OCCIDENTAL PETROLEUM QATAR Ltd, Produced Water Handling Facility –HALUL ISLAND

Project
Produced Water Handling Facility –HALUL ISLAND

Scope
EPC contract for Electrical Controls, Telecommunications & Instrumentation required for construction of a produced water handling facility on Halul Island to separate water from the crude oil export line from Oxy production platform PS1

Project Scope Definition
Design, Procurement, Installation & Commissioning of:-

  • 33KV Substation
  • MV Power transformers
  • LV Distribution transformers
  • HT< Switchgear
  • Indoor & Out door Lighting systems
  • Field starter panels for Flare Controls
  • DCS Systems
  • ESD / F&G system conforming to IEC 61508 SIL-2
  • Microwave, UHF Communication Systems
  • Field Instrumentation.